Thrust
Committee to Review the Slow Pace of Capacity Addition
Mr. Sushil Kumar Shinde, Minister for Power will head a
committee comprising of former Power Secretaries P Abraham,
RV Shahi, Anil Razdan and two representatives of Independent
Power Producers (IPPs) to review the slow pace of capacity
addition. The said Committee is expected to make necessary
recommendations to give a much needed push for attaining
the proposed a capacity addition of 78,577 MW by the end
of 2011-2012.
National Electricity Fund
The Planning Commission has proposed setting up a National
Electricity Fund to finance development of power transmission
and distribution network by state utilities. The proposed
corpus of the fund would be Rs 1,00,000-1,50,000 Crore.
Lex Loci
Regulation to Make Renewable Energy Mandatory for SEZs
The Ministries of Commerce & Industry and New &
Renewable Energy are reportedly working on the modalities
of a regulation to make use of renewable energy mandatory
for Special Economic Zones (SEZ).
It is reported that the proposed regulation may mandate
to create a mechanism for producing 1KW of renewable energy
for one hectare of development in every SEZ, which would
save on traditional fuel like coal and diesel.
Rulings
Interim Relief Refused
A Bench headed by Justice B.N. Agarwal of the Apex Court
was not inclined to grant an interim relief to the Government,
which challenged the Madras High Court ruling quashing its
notices demanding excise duty from three power firms.
Policy Corner
Tariff Norm for Power Procurement Further Tightened
The guidelines for tariff determination for power procurement
by distribution licensees have been tightened. The revised
guidelines provide for inter alia the following:
i. A multi-part tariff structure featuring separate capacity
and energy components of tariff will ordinarily form the
basis for bidding and tariff will be paid and settled for
each payment period not exceeding one month.
ii. Procurement under Case-2 where procurer offers a captive
fuel source for concurrent development and use for power
production covered under the procurement query would also
have a multi-part tariff structure featuring separate capacity
and energy components of tariff.
iii. In cases where the procurement process permits bidders
to submit combined capacity and energy charges, the charges
proposed shall be firm for each of the years of the term
of the Power Purchase Agreement (PPA), and no escalation
of tariff shall be permitted over and above the rates quoted
by the seller in the price bid.
iv. In Case-1 procurement, the bidder, in case the supply
is proposed from a station to be set-up, should be required
to submit along with its bid, documents in support of having
initiated specific actions for project preparatory activities
in respect of site identification and land acquisition,
environmental clearance for the power station, forest clearance
(if applicable) for the land for the power station, fuel
arrangements, and water linkage.
v. If the Bidder is a trading licensee, it shall have executed
exclusive power purchase agreement(s) for the quantity of
power offered in its Bid and shall provide a copy of the
same as part of its Bid. In such a case, the Bidder shall
ensure that the entity with which it has executed the exclusive
power purchase agreement for supply of power under the bid
process has completed the project preparatory activities.
vi. Foreign exchange rate variation would be permitted
in the payment of energy charges in the stipulated cases,
if the bidder chooses to supply power using imported coal
or imported gas (RLNG) for long term procurement under Case-1.
vii. In cases where the procurer mandates use of imported
fuel for use in a coastal power station in Case-2 procurement
query or where the bidder chooses to supply from a power
station using imported fuel under Case-1, the bids may be
invited for base energy charge for the first year to be
escalated as per the indices identified in the RFP. Such
energy charge would have three components, namely imported
fuel component in US Dollars/unit; transportation of fuel
component in US Dollars/unit; and inland fuel handling component
in Indian Rupees/unit.
Priority to Power Sector over LPG Production
The Empowered Group of Ministers (EGOM) has decided to
give the power sector priority over LPG production in the
allocation of gas from Reliance’s Krishna-Godavari
fields. This would help to reduce power shortages by the
optimum utilization of as many as 40 gas-based plants that
face fuel shortages in the country
Government Plans Setting up a Renewable Power Exchange
The Government is planning to set up a renewable power
exchange that would issue certificates to surplus states
which can be sold to deficit states looking to fill the
portion of their power grid mandatory reserved for green
energy.
The gross installed capacity of grid interactive renewable
power in the country is estimated at 11,273 MW, which accounts
for 8% of the country’s installed generation capacity.
The government has set a target of an additional 13,500
MW renewable energy by the end of 11th Five-Year Plan.
.